Project overview
From the project Fact Sheet, November 2026
On May 1, 2026, Weaver’s Cove Industrial Park LLC (“WCIP”) the Project Proponent, submitted a Fill Management Plan application (“FMP”) to Massachusetts Department of Environmental Protection (“MassDEP”) for the next phase of site development (the “Project”) of 1 New Street (the “Property”) in Fall River. The Proponent is requesting approval from MassDEP to allow soil re-use in order to fill, cap and develop the vacant Property. This is WCIP’s summary of the Project and review process that MassDEP will follow.
Purpose: WCIP seeks to import suitable fill material to raise the grades at the Property to cap the site in order to prepare for future redevelopment, creating new jobs and adding to the Fall River tax base, while at the same time placing additional fill upon historic Shell operations.
MassDEP will review WCIP’s application and will evaluate the criteria governing what soils may be accepted by the Project and implementation by the Proponent after the Public Involvement Process has been completed.
- Facility
- Weaver’s Cove Industrial Park LLC
- Location
- One New Street, Fall River MA
- Fill Management Plan submitted
- May 1, 2026
Documents
Each document is available in English, Spanish, Portuguese and Haitian Creole. All files are PDFs.
- Español: Traducciones de cortesía. Si hay diferencias, prevalece el original en inglés.
- Português: Traduções de cortesia. Em caso de diferença, prevalece o original em inglês.
- Kreyòl ayisyen: Tradiksyon pou ede w konprann. Si gen diferans, se orijinal angle a ki konte.
Information Sheet
Fill Management Plan
Stormwater Management Report
How to comment
Public Hearing: Morton Auditorium on December 8, 2026, at 6:00pm. The Morton Auditorium is located at James Madison Morton Middle School, 1135 N Main Street, Fall River, MA, 02720.
- WCIP will hold a public meeting, accept comments, respond to all of them and submit the comments and responses to DEP for review.
- After its review, MassDEP will issue a proposed decision with another 30-day public comment period.
Contacts
-
David A. Murphy PE
Murphy & McMahon Engineering
-
Joseph Salvetti LSP
Civil & Environmental Consultants, Inc.
Comment online